Phase 1 Timeline

2016 Timeline

June 2nd, 2016- The Township will be holding bid applications for construction of the Complete Streets project.

June 7th, 2016- The Township award the construction bid to Flanagan's Contracting Group, Inc.

June 22nd, 2016- The Township, Arterial and Flanagan's Contracting Group held a pre-construction meeting.    

July 13th, 2016- Millburn anticipates beginning construction for Complete Streets in the Downtown area.

July 18th, 2016- Milling of Main Street and demolition of sidewalk on Main Street and Millburn Ave to begin.

July 25th, 2016- Electrical conduits will be dug and placed for future underground wiring. The drainage system will be installed and continuation of curbs and sidewalks being framed and poured with concrete.

August 1st, 2016- Continuation of curbs and sidewalks being framed and poured with concrete. Utilities will continue to work on Main Street.

August 8th, 2016- Demolition and preparation of sidewalk on Millburn Ave.

August 15th, 2016- Pouring of concrete road way on Main Street.

August 22nd, 2016-  Framing and pouring of curbs and sidewalks on Millburn Ave.

August 29th, 2016- Placing of conduits and construction of sidewalk and curbs on Main Street.

September 5th, 2016- Opening of Main Street and construction of sidewalk and curbs on Main Street.

September 12th, 2016Completed pouring concrete sidewalk and curbs on north side of Millburn Ave down to the entrance of Town Hall.

September 19th, 2016- Began demolition on south side of Millburn Ave

September 26th, 2016- Set granite blocks on Main Street and prepared sidewalk and curbs on Millburn Ave

October 3rd, 2016- Completed pouring concrete sidewalk and curb on the south side of Millburn Ave

October 10th, 2016- Completed pouring concrete for flexible parking along the south side of Millburn Ave  

October 17th, 2016- Set granite millstones on Main Street

October 24th, 2016- Installed drainage west of Town Hall and opened flexible parking from Dunkin Donuts to Starbucks

October 31st, 2016- Set pavers on the Starbucks and Charlie Brown corners and poured concrete walkway west of Town Hall

November 7th, 2016- Completed pouring of sidewalk west of Town Hall

November 14th, 2016- Milling, paving, and striping of Millburn Ave from Spring Street to Main Street

November 21st, 2016- Setting pavers and ramp at the Crepe corner

November 28th, 2016- Began milling of new road by Town Hall

December 5th, 2016- Completed the corners at Gotham and La Creperie

December 12th, 2016- Poured curbs for the new roadway

December 19th, 2016- Poured majority of sidewalks along new road

January 5th, 2017- Installed new traffic lights at Main St and Millburn Ave

January 19th, 2017- Continuing grading and preparation along the new road area 

January 26th, 2017- Installing light fixtures throughout downtown area

February 2nd, 2017- Completed construction in parking Lot 5


Complete Streets Construction Update 2/2/2017
Over the next week Flanagan’s Construction will be working on the following tasks: 
Preparing grading of the new road by Town Hall
Installing traffic and street lights throughout the Downtown
Completed construction to create circulation for the parking lot 5
**All work is weather dependent**

Work completed January 2017
Saw-cutting sidewalk along new road  
Installation of additional benches  
Continuing to pour sidewalk along new road

Please remember that parking is now Pay-by-Plate. For more information on Pay-by-Plate parking please visit the Parking Webpage