Complete Streets Construction Update 9/12/2016
A Look at the Week Ahead:
Main Street, between Essex Street and Millburn Ave, is now open for vehicular traffic and pedestrian traffic. Please be aware of new traffic patterns.
The following traffic patterns regarding Main Street have changed:
• No left turn from Millburn Ave. to Main St.
• No left turn from Essex St. to Main St.
• No left turn from Main St. to Essex St.
Over the next week Flanagan’s Construction will be working on the following tasks:
Finishing pouring concrete sidewalk and curbs on north side of Millburn Ave down to the entrance of Town Hall
Beginning to demo and install new sidewalks and curbs along south side of Millburn Ave
Setting basalt pavers on Main Street
Pouring foundation for lighting conduits
*Work on Millburn Ave down to Hagan Daz is expected to be completed by the end of next week. All schedules are subject to change and are dependent on weather conditions.
*Access to stores on Millburn Ave (from Town Hall to Starbucks) will periodically have limited access due to the demolition pouring of sidewalks. If possible, please use backdoor access to stores via the Courtyard.
Work completed during the week of 9/5/2016:
Striping on Main Street roadway
Continuing to demo and prepare new sidewalks along Millburn Ave
Pouring concrete sidewalk and curbs on Millburn Ave
Preparing to set basalt pavers