[ARCHIVED] Complete Streets Construction Update

Complete Streets Construction Update 10/24/2016
Over the next week Flanagan’s Construction will be working on the following tasks:
Setting granite corner stone’s on Main Street (Fiamma Pizza)
Installing new custom benches on Main Street
Setting basalt pavers on the south side of Millburn Ave
Installing drainage along driveways on Millburn Ave
Demolition and milling of sidewalk west of Town Hall
Pouring concrete sidewalk and curb in front of School House Plaza

Work completed during the week of 10/17/2016:
Set granite corner stone’s on Main Street
Completed pouring concrete for existing corners on Millburn Ave and Main Street
Installed conduits and drainage in front of School House Plaza
Poured concrete sidewalk and curb in front of School House Plaza

Businesses on the south side of Millburn Ave are open!
Haagen-Daz
Green Nectar Juicery
Millburn Frame Shop
Daren Michaels Jewelry
Elements for Style
Avalon Salon
Trend Consignment
Roxy Shoes
Bedazzeled Jewelry
Bow Tie Cinemas
Gambert Custom Shirts
Emack & Bolios
Schultz & Blaustein
DH Lighting

REMINDER: Main Street, between Essex Street and Millburn Ave, has been open for vehicular traffic and pedestrian traffic.

Please be aware, the following traffic patterns regarding Main Street have changed:
• No left turn from Millburn Ave. to Main St.
• No left turn from Essex St. to Main St.
• No left turn from Main St. to Essex St.

Phase 1 of Complete Streets construction is expected to last through the fall with an anticipated completion date in November. The Downtown area will remain open for business and pedestrian foot traffic during construction.

Complete Streets Webpage